Automatic Pool Cover Coordination Checklist

A new-construction coordination checklist for automatic pool covers, covering measurement, track type, vault, drainage, power, coping, and equipment location.

Direct answer

Use this sheet before cover-related structure or routes are concealed. Record dimensions in one unit, identify the drawing revision and obtain a named, dated confirmation for geometry, track, housing, drainage, power and controls. The revised HTML and existing PDF are matching planning records, not installation approval.

Key takeaways

  • Track type and vault size are structural decisions, not finish options.
  • Confirm drainage and power routes before the work that would conceal them.
  • Coping and deck slope must match the chosen track.
  • This page does not cover repair, fabric replacement, or motor troubleshooting.

Missing reservations can mean reopening completed work. Use this checklist with the designer and installer before excavation and before concealing cover details. Print the matching checklist PDF.

Revision 2, 8 October 2026; the existing v1 download address is retained. Record project/site: ___; system/model: ___; manual edition: ___; drawing set/revision: ___; dimension unit: ___ (choose inches or mm for the whole sheet).

Measurement and geometry

Scroll horizontally to read all columns.

Item Value / unit Drawing no. / revision Confirmed by / signed date
Length at waterline
Width at waterline
Corner radii / freeform offsets
Waterline to finished deck
Bench, spa, or raised bond beam

Takeaway: Hold geometry release until measurement datums, units and every dimension are confirmed by the installer.

Plan showing width and length measurement lines, end cover box, drain route and operator position.
Planning illustration. Confirm the actual measurement datums and a control location with full cover visibility against the selected manual.

Track, vault, and structure

Scroll horizontally to read all columns.

Item Choice / dimensions Drawing no. / revision Confirmed by / signed date
Track type Undertrack / top track / other
Vault or bench location
Vault width, depth, and lid
Vault drain and discharge
Recess or housing for the leading edge

Takeaway: Do not form the housing or conceal its drain while size, lid access, track detail or discharge remain unresolved.

Power, coping, and equipment

Scroll horizontally to read all columns.

Item Note / status Drawing no. / revision Confirmed by / signed date
Electric or hydraulic drive
Conduit / hose path to the pad or room
Control location and line of sight
Coping profile compatible with the track
Deck slope away from track and vault
Equipment listed on the BOM template

Takeaway: Hold route closure and coping installation until power/hose paths, control visibility and the edge detail are signed off. These are editorial coordination holds; contractual release authority must be assigned in the project agreement.

The public Hydramatic Undertrack/Top Recess manual (2007), pre-site and track sections, illustrates recess drainage and coping interfaces; its Toptrack manual (2007), power and hose sections, specifies control visibility. The undated track-space drawing supplies measurement datums. Use these only for that system and obtain the applicable current documents for the installed model.

Do not write a blanket safety-standard claim on this sheet. If a named certification matters, attach the product document for that configuration.

Beige automatic cover closed across a rectangular pool with tracks along the coping.
Coping and deck slope must match the chosen track before stone is set.

Related reading: the pool covers hub, the construction process, and the equipment BOM template.

Frequently asked questions

Can this be used for a retrofit cover?

It can flag the same coordination items, but an existing pool often lacks a vault, drain, or conduit path. Treat retrofit as a separate project, not a shortened new-construction list.

Does this certify a safety standard?

No. The checklist does not claim that a cover, pool, or installation meets a named safety standard. Certification belongs to a specific product and configuration with its own documentation.

Sources

  1. Hydramatic Undertrack and Toptrack/Recess Installation Manual (2007), pre-site checks and track details — Aquamatic
    Accessed October 8, 2026.
  2. Hydramatic Toptrack Installation Manual (2007), bench, hose and control layout — Aquamatic
    Accessed October 8, 2026.
  3. How to Measure Track Space (undated drawing) — Aquamatic
    Accessed October 8, 2026.

About the author

Editor

Lauren Crowe writes and reviews Fielder Pools guides from public technical sources. She is an editor, not a licensed engineer or contractor.

  • Source checks against manufacturer manuals and official guides
  • Documented correction and update workflow
  • Clear separation of sourced fact and editorial judgment