Resources

How Are Fiberglass Pools Installed? Base & Fill

Step-by-step guide to how fiberglass pools are installed: excavation, compacted crushed-stone base, crane set, plumbing, bonding, and synchronized backfill.

Direct answer

A one-piece inground fiberglass pool is installed in six stages: securing permits and underground utility locates, digging the shaped excavation, leveling and compacting a crushed-stone base, lowering the factory-molded shell by crane, completing pressure-tested Schedule 40 PVC plumbing and NEC 680.26(B)(2) equipotential bonding, and placing compacted 6- to 12-inch backfill lifts simultaneously with interior water fill before pouring the perimeter collar and deck.

How are fiberglass pools installed? Crews install a one-piece inground fiberglass pool across six stages: securing permits and utility locates, excavating to shell contour, leveling and compacting a crushed-stone base, lowering the pre-formed vessel by crane, completing pressure-tested plumbing and perimeter bonding, and backfilling in compacted 6- to 12-inch layers simultaneously as water fills the basin.

Review this sequence alongside the pool construction hub, our gunite pool vs fiberglass structural comparison, the soil testing and excavation planning guide, and the site-built concrete pool construction stages guide before locking your excavation and crane schedule.

What are the step-by-step fiberglass pool installation stages?

One-piece fiberglass pool installation follows six sequential field stages: permitting and utility clearance, contour excavation, compacted granular bedding, crane shell placement, rough plumbing with electrical equipotential bonding, and synchronized water filling with layered backfill leading into decking and barrier sign-off. Every later stage buries the one below it, so each hold point must pass before concealment.

Unlike site-built concrete pools, one-piece fiberglass shells arrive factory-molded with built-in steps, ledges, and a smooth gelcoat surface already cured. That pre-formed construction shifts field risk away from on-site shell framing and onto excavation accuracy, uniform base support, crane rigging, and pressure-balanced backfilling.

Six-panel engineering infographic showing fiberglass pool installation stages: permits and excavation with utility locate and 2-foot spoil setback, laser-leveled ASTM D448 crushed-stone base, crane shell placement with 20-foot power-line buffer, Schedule 40 PVC plumbing and #8 copper bonding, equalized water fill with 6- to 12-inch backfill lifts, and perimeter collar with one-fourth inch per foot sloped deck
The six coordinated stages of one-piece inground fiberglass pool installation, pairing each construction phase with its primary safety, bedding, plumbing, bonding, or drainage verification check.

The table below aligns each installation stage with the governing code checkpoint or construction requirement that closes it before the next crew mobilizes:

Scroll horizontally to read all columns.

Stage Core field scope Controlling check or code benchmark Typical duration
1. Design, permits, and utility locates Site plan, setbacks, multi-permit approvals, and underground utility marking Utility locations identified prior to digging under OSHA 1926.651(b)(1); multiple local permits issued 1 to 2 weeks design; 1 to 4 weeks permits
2. Contour excavation and site protection Excavating basin depth, dewatering groundwater, and protecting adjacent footings Cave-in protection at 5 feet (1.52 m) or deeper under OSHA 1926.652(a)(1); spoil kept 2 feet (0.61 m) back 1 to 3 days
3. Granular base preparation Placing, screeding, and compacting crushed stone or sand across the floor Uniformly level, compacted foundation using graded coarse aggregate classified under ASTM D448 Included in dig and set prep
4. Crane delivery and shell set Hoisting and seating the one-piece shell squarely on the prepared base 20-foot power-line work-zone check under OSHA 1926.1408(a)(2); zero workers under suspended load Few hours to 1 to 2 days
5. Plumbing, bonding, and synchronized backfill Installing Schedule 40 PVC lines, bonding loop, and rising water with 6- to 12-inch backfill lifts Pressure-tested piping (e.g., 35 psi municipal check) and NEC 680.26(B)(2) 3-foot bonding grid 3 to 5 days
6. Collar, coping, deck, and barrier final Pouring perimeter collar and sloped deck, installing safety fence, and final sign-off Deck sloped at least one-fourth inch per foot; self-latching exterior gate latch at least four feet high 1 to 3 weeks

Permits, setbacks, and pre-dig excavation safeguards

Before an excavator enters the yard, residential pool projects commonly require several coordinated permits. As one municipal example, the City of Orlando Residential Swimming Pool and Spa Checklist requires a minimum of three permits (covering building and engineering, electrical, and plumbing or gas where applicable), enforces a minimum 5-foot setback from pools and decks to property lines under Section 58.958, and requires excess excavated dirt to be hauled offsite rather than spread across the lot. Organize those municipal submittals and HOA conditions early using our pool permit, HOA approval, and utility-locate register.

Once permits clear, federal construction safety standards under OSHA 29 CFR 1926.651 and OSHA 29 CFR 1926.652 govern the open pit:

  • Underground utility locates: Under OSHA 1926.651(b)(1), the estimated locations of sewer, telephone, fuel, electric, and water lines must be determined prior to opening an excavation.
  • Cave-in protection and egress: Under OSHA 1926.652(a)(1), excavations 5 feet (1.52 m) or deeper require an adequate protective system unless dug entirely in stable rock, while trenches 4 feet (1.22 m) or deeper require a ladder, stairway, or ramp within 25 feet (7.62 m) of lateral travel under OSHA 1926.651(c)(2).
  • Spoil setbacks and adjacent foundations: Under OSHA 1926.651(j)(2), excavated soil, stone stockpiles, and equipment must stay at least 2 feet (0.61 m) back from the excavation edge; under OSHA 1926.651(i)(1), shoring, bracing, or underpinning must protect adjoining buildings, walls, or footings endangered by digging.
  • Rainstorm and groundwater checks: Under OSHA 1926.651(h)(1), (h)(3), and (k)(1), crews must divert surface runoff, control accumulating groundwater, and have a competent person inspect the excavation daily and after every rainstorm.

Plumbing, pressure testing, bonding, and final barrier inspection

After the shell is seated and leveled, installers run Schedule 40 PVC recirculation piping for skimmers, returns, and drains, keeping buried lines continuously supported to prevent sagging under backfill weight. Engineering practice for buried thermoplastic piping is codified in ASTM D2321, which establishes stable granular embedment environments, while New York Sanitary Code Section 6-1.29 Item 9.2.2 caps recirculation pipe velocities at 6 feet per second under suction, 10 feet per second under pressure, and 3 feet per second in gravity flow, and Item 9.3 requires continuous pipe support with suction piping sloped in one direction toward the pump.

Every buried plumbing circuit must pass a documented pressure test before backfill or decking conceals it—for instance, Orlando’s pool deck and piping inspection verifies a 35 psi reading on the piping pressure gauge. Track circuit boundaries and test records with our underground plumbing hydrostatic pressure-testing checklist.

Electrical equipotential bonding must likewise pass inspection before concrete or pavers cover the perimeter. Under North Carolina OSFM guidance for NEC Section 680.26(B)(2), an equipotential bonding grid must extend at least 3 feet outward around the pool contour, and a single #8 bare copper conductor installed 18 to 24 inches from the pool edge is permitted to establish that perimeter plane around non-conductive vessels. Document your inspector’s edition and layout using the equipotential bonding and electrical inspection handoff.

Before final sign-off, perimeter decking must shed water away from the basin—New York Sanitary Code Items 5.9.1 and 5.9.2 require at least a one-fourth inch per foot slope to deck drains or grades, with drains serving no more than 400 square feet and spaced at most 25 feet apart—and safety barriers must meet local code. In Orlando’s municipal checklist, pools 2 feet or deeper and 36 square feet or larger require a permitted fence under Section 58.959, and exterior access gates must be self-closing and self-latching with latches mounted at least four feet above ground and operable only from inside the enclosure.

How do the crushed-stone base, crane set, and simultaneous backfill protect the shell?

A fiberglass pool shell relies on continuous, uniform contact across its floor base and balanced lateral pressure along its walls because it is a thin fiber-reinforced plastic vessel rather than a rigid site-cast concrete mass. Setting the shell onto a pre-leveled, compacted granular bed and advancing 6- to 12-inch compacted backfill lifts in lockstep with interior water fill keeps the composite laminate from settling, bulging, or cracking.

Engineering cross-section of an installed one-piece fiberglass pool shell showing pre-leveled ASTM D448 compacted crushed-stone floor base, 6- to 12-inch backfill lifts balanced against synchronized interior water fill, hydrostatic relief underdrain pipe, continuously supported Schedule 40 PVC line, NEC 680.26(B)(2) #8 bare copper perimeter ring 18 to 24 inches from edge, and concrete collar with deck sloped away at one-fourth inch per foot
Cross-section of an inground fiberglass vessel illustrating uniform floor bearing on compacted crushed stone, balanced lateral water-and-backfill loading, hydrostatic drainage relief, supported PVC plumbing, and perimeter bonding.

Leveling the granular base without point loads

Structurally, fiberglass is a fiber-reinforced plastic composite—most commonly reinforced with E-glass alumino-borosilicate fibers containing less than 1% weight-by-weight alkali oxides—molded into a thin shell that is non-conductive, non-magnetic, chemically inert under many circumstances, and strong for its weight. Because that thin shell spans the entire pool floor in one piece, any hollow void or protruding high spot underneath concentrates the full water load onto a narrow patch of laminate.

Installers therefore construct a level, compacted foundation of crushed stone or sand across the bottom of the excavation before the crane lowers the vessel. Coarse aggregates used in engineered bedding and drainage zones are designated by mechanical sieve ranges under ASTM D448, allowing builders and engineers to specify clean, consistent stone gradation rather than unscreened native soil. If the shell sits out of level during initial dry-fitting, crews lift the vessel back off the bed and re-screed the granular base rather than wedging isolated shims underneath the floor.

Synchronizing water fill with 6- to 12-inch backfill lifts and groundwater relief

Once the shell rests evenly on the prepared base and initial plumbing connections are in place, backfilling and water filling proceed together. Backfill material is placed around the outside perimeter in 6- to 12-inch layers, compacting each lift thoroughly before adding the next while interior water rises to match exterior fill elevation. Skipping that synchronization—either piling dense backfill against an empty wall or filling an unsupported shell—is the single most common installation error and leads directly to inward wall bulging, outward bowing, or laminate cracking.

Groundwater beneath and around the excavation must be managed for both construction and long-term ownership. Under New York Sanitary Code Item 5.0, swimming pools must be designed and constructed to withstand all anticipated loading in both full and empty conditions, with a hydrostatic relief valve or suitable underdrain system provided. During active excavation, OSHA 1926.651(h)(1) and (h)(3) similarly require pumping or drainage controls whenever groundwater accumulates or surface runoff threatens the pit. Coordinate the upper perimeter collar and coping edge with our types of pool coping guide so deck loads bear on compacted backfill and collar concrete rather than on the thin gelcoat lip.

How long does it take to install a fiberglass pool?

Once local permits are issued, installing a fiberglass pool takes an average of 2 to 6 weeks from groundbreak to finished decking and barriers—substantially faster than the 4 to 8 weeks typical for vinyl-liner pools or the 8 to 12+ weeks required for site-built concrete pools. Because the shell arrives factory-molded with steps, ledges, and gelcoat already finished, crane placement itself often takes only a few hours.

Compare fiberglass installation speed and design scope against the two other primary inground construction methods:

Scroll horizontally to read all columns.

Inground pool type Typical install duration Factory mold vs on-site shape Primary schedule advantage or constraint
One-piece fiberglass shell 2 to 6 weeks Limited to factory shell molds Pre-formed steps, ledges, and gelcoat eliminate on-site shell framing and plaster curing
Vinyl-liner pool 4 to 8 weeks Highly customizable panel layouts Faster than concrete, but requires panel assembly, floor finishing, and periodic liner replacement (7 to 12 years typical durability)
Concrete (gunite or shotcrete) 8 to 12+ weeks Complete on-site shape customization Longest calendar due to rebar, shotcrete placement, shell curing, tile, and interior finish start-up

Breaking the fiberglass schedule into discrete work windows clarifies where calendar time actually goes before and after crane day:

Scroll horizontally to read all columns.

Project phase Typical duration window Primary delay driver
Design and planning 1 to 2 weeks Selecting shell mold, elevation datum, and poolside add-ons
Permitting and approvals 1 to 4 weeks Municipal review queues, zoning setbacks, and HOA sign-off
Excavation and base prep 1 to 3 days Rain turning the dig into mud, rocky ground, or groundwater pumping
Shell delivery and crane placement Few hours to 1 to 2 days Overhead utility clearance coordination and tight yard access
Plumbing, electrical, and backfill 3 to 5 days Piping pressure-test holds and electrical bonding inspection scheduling
Decking, fencing, and final touches 1 to 3 weeks Custom coping, hardscape area, barrier installation, and weather

Weather and permit queues dominate schedule variance. Even a few rainy days during excavation or decking can turn the yard into mud and push completion back by a week or more, and OSHA 1926.651(k)(1) mandates competent-person re-inspection of open excavations after every rainstorm before crews resume work.

Can you install a fiberglass pool shell yourself?

Homeowners can act as project coordinators for site planning, permit paperwork, and landscaping, but crane hoisting, deep excavation safety, licensed electrical bonding, and warranty-compliant backfilling make a full DIY fiberglass pool installation impractical and high-risk for most property owners. Many fiberglass shell manufacturers explicitly require qualified professionals to execute critical installation stages to keep structural warranty coverage intact.

Use the boundary table below to separate homeowner-manageable coordination tasks from regulated trade and safety holds before ordering a shell kit:

Scroll horizontally to read all columns.

Installation task DIY / homeowner role Why licensed or qualified pros control execution
Site plan, permits, and HOA coordination Gather survey, submit paperwork, track inspection bookings Municipal building departments still enforce plan review, setbacks, and hold-point sign-offs
Excavation and cave-in protection Mark layout and clear yard obstacles Excavations 5 feet (1.52 m) or deeper require protective systems under OSHA 1926.652(a)(1), utility locates under 1926.651(b)(1), and footing support near structures
Crane delivery and shell lowering Confirm driveway access and clear overhead branches Crane crews must enforce 20-foot power-line rules under OSHA 1926.1408, non-conductive tag lines, and zero-occupancy load zones
Plumbing and synchronized backfill Inspect level checks and verify pressure-test logs Improper 6- to 12-inch lift compaction or unbalanced filling is the leading DIY mistake causing shell bulging or cracking
Electrical wiring, GFCI, and bonding Confirm equipment pad placement and inspection date A licensed electrician must install GFCI protection, pump and lighting circuits, and NEC 680.26(B)(2) perimeter bonding

Can a fiberglass pool be installed above ground or semi-inground?

Standard inground fiberglass shells cannot simply be set above ground without structural engineering, because a thin composite vessel depends on uniform base and surrounding earth support unless specifically engineered to withstand full-and-empty free-standing loads. Any elevated or semi-inground installation must also satisfy local accessory-structure setbacks, floodplain elevation rules, and permanent-pool electrical bonding codes.

Three documented engineering and code checks govern raised, sloped-yard, or semi-inground fiberglass pool proposals:

  1. Full-and-empty structural load certification: Under New York Sanitary Code Item 5.0, every swimming pool must be designed and constructed to withstand all anticipated loading in both full and empty states. Standard thin-shell fiberglass vessels built for uniform granular backfill cannot resist outward water thrust in an unbraced above-ground wall without manufacturer-approved structural framing or an engineered retaining wall system.
  2. Elevated structure setbacks and floodplain elevation: Raising a pool or surrounding deck changes how zoning offices classify the structure. Under City of Orlando rules, decks elevated 3 feet or more must comply with accessory-structure setbacks under Section 58.901 rather than standard flat-deck setbacks, and pools or decks located inside a 100-year floodplain must elevate mechanical and electrical equipment at least one foot above the established Base Flood Elevation.
  3. Mandatory equipotential bonding regardless of elevation or paving: According to North Carolina OSFM guidance on NEC Section 680.26(B)(2), an equipotential bonding grid is required for any permanent pool—inground or aboveground—whether or not a paved deck surrounds the basin.

If your backyard slopes steeply and requires partial elevation or retaining walls, coordinate grades and drainage outlets early with our retaining wall construction guide for sloped backyards.

What are the installation downsides, crane access limits, and scope cost drivers?

The main installation downsides of one-piece fiberglass pools are fixed catalog mold geometry, strict crane swing and overhead power-line clearances, and zero margin for sloppy base preparation or unbalanced backfill. Rather than quoting universal price estimates, evaluate the physical site conditions—crane reach, overhead utilities, rocky ground, high groundwater, dirt haul-off, and extra backfill—that expand installation scope.

Engineering site-access and elevation diagram showing a mobile crane lifting a fiberglass pool shell over an existing house below a 20-foot OSHA 1926.1408 overhead power-line clearance zone, with a non-conductive tag line, zero workers beneath the suspended load under 1926.651, cave-in protection at 5 feet or deeper under 1926.652, 2-foot minimum spoil setback, and an OSHA Table A voltage clearance strip from 10 to 45 feet
Crane hoisting geometry and site clearance constraints for delivering a one-piece fiberglass shell, summarizing federal overhead power-line buffers, suspended-load exclusion zones, and excavation spoil setbacks.

Under OSHA 29 CFR 1926.1408, before lifting a fiberglass shell, the crane operator must determine whether any part of the boom, load line, rigging, or suspended shell at maximum working radius could come closer than 20 feet to an overhead power line. When the work zone enters that 20-foot envelope, crews must select one of three federal compliance paths: have the utility de-energize and visibly ground the line, maintain a 20-foot clearance with encroachment precautions, or verify exact line voltage—which the utility must provide within two working days under 1926.1408(c)—and maintain the minimum clearance distances in Table A:

Scroll horizontally to read all columns.

Overhead power line voltage (nominal, kV, AC) Minimum crane clearance distance (feet) Mandatory operational control
Up to 50 kV 10 feet Pre-lift crew meeting, elevated warning line or spotter, and non-conductive tag lines
Over 50 to 200 kV 15 feet Utility voltage confirmation within two working days plus encroachment controls
Over 200 to 350 kV 20 feet Matches default 20-foot clearance buffer with active boom encroachment safeguards
Over 350 to 500 kV 25 feet Expanded Table A approach boundary or utility de-energizing and visible grounding
Over 500 to 750 kV 35 feet High-voltage transmission standoff enforced with dedicated spotter or range limiter
Over 750 to 1,000 kV 45 feet Maximum Table A clearance envelope; verify voltage with utility before crane setup

Whenever tag lines guide the suspended shell near power lines, OSHA 1926.1408(b)(2) requires non-conductive tag lines, and OSHA 1926.651(e) prohibits any worker from standing underneath the suspended fiberglass shell at any point during the pick.

Mold limits and site conditions that expand installation scope

Beyond crane geometry, five physical site and manufacturing constraints define the practical downsides and primary scope drivers of fiberglass pool installation:

  • Fixed factory mold dimensions: Fiberglass laminates cure in the factory—polyester resins contract 5 to 6% and epoxy resins about 2% during curing—so the delivered shell arrives as a rigid catalog geometry whose steps, benches, and depth profile cannot be reshaped on site.
  • Rocky soil and difficult excavation: Encountering bedrock, boulders, or unstable strata expands excavation equipment time, requires protective sloping or shoring at 5 feet (1.52 m) or deeper, and can require engineered underpinning if digging approaches adjacent house or wall footings.
  • Water-table dewatering and drainage: High groundwater requires continuous pumping during excavation under OSHA 1926.651(h)(1), diversion ditches for surface runoff, and a permanent hydrostatic relief valve or underdrain assembly so groundwater cannot lift the vessel.
  • Utility relocation and offsite dirt haul-off: Buried electric, sewer, gas, or irrigation lines discovered during pre-dig locates must be rerouted before excavation, and municipal grading rules such as Orlando’s require hauling all excess excavated dirt offsite rather than spreading it in the yard.
  • Extra engineered backfill and hardscape scope: Over-excavated zones, sloped yards, and wide custom concrete or paver decks increase graded crushed-stone backfill tonnage, concrete collar volume, drainage piping, and safety-barrier fencing runs.

Before signing an installation contract, verify crane pad access, overhead line clearances, soil excavation contingencies, and synchronized backfill responsibilities in writing alongside our pool construction hub.

Frequently asked questions

What happens first before excavating for a fiberglass pool?

Installation moves through six coordinated stages: permits and underground utility locates, contour excavation with cave-in protection at 5 feet or deeper, leveling and compacting a crushed-stone base, crane shell placement, pressure-tested Schedule 40 PVC plumbing with NEC 680.26(B)(2) perimeter bonding, and simultaneous water filling with 6- to 12-inch compacted backfill layers followed by perimeter decking and safety barrier inspections.

Why must water fill rise alongside backfill on a fiberglass pool?

A one-piece fiberglass shell is a thin fiber-reinforced plastic vessel rather than a thick site-cast reinforced concrete basin. Raising interior water in step with 6- to 12-inch compacted exterior backfill lifts equalizes inward earth load and outward water pressure so the shell walls do not bulge, bow, or crack.

Which site factors affect a fiberglass pool installation timeline?

Once permits are approved, fiberglass pool installation averages 2 to 6 weeks overall, broken down into 1 to 3 days for excavation, a few hours to 2 days for crane delivery and placement, 3 to 5 days for plumbing and electrical work, and 1 to 3 weeks for decking, fencing, and final touches. Rain, local permitting queues, and tight site access can extend that schedule.

Which fiberglass pool installation steps require licensed professionals?

Homeowners can coordinate planning and permitting, but crane operation near power lines, excavation safety at 5 feet or deeper, licensed electrical bonding and GFCI wiring, and manufacturer warranty rules generally require qualified professionals. Improper backfilling is the most common DIY failure mode and can bulge or crack the shell.

Does a non-conductive fiberglass pool still require electrical bonding?

Yes. Even though fiberglass composite is non-conductive, NEC Section 680.26(B)(2) requires a perimeter equipotential bonding grid extending at least 3 feet around every permanent inground or aboveground pool—whether paved decking is installed or not—and permits a single #8 bare copper conductor placed 18 to 24 inches from the pool edge.

Sources

  1. 29 CFR 1926.651 — Specific Excavation Requirements — Occupational Safety and Health Administration (OSHA)

    Paragraphs (b), (c), (e), (h), (i), (j), and (k).

    Federal construction safety rules governing underground utility locates, trench egress, suspended load exclusion, dewatering, adjacent structure support, 2-foot spoil setbacks, and rainstorm inspections.

  2. 29 CFR 1926.652 — Requirements for Protective Systems — Occupational Safety and Health Administration (OSHA)

    Paragraph (a)(1).

    Federal cave-in protection threshold requiring sloping, benching, shoring, or shielding in excavations 5 feet (1.52 m) or deeper outside stable rock.

  3. 29 CFR 1926.1408 — Power Line Safety (up to 350 kV) — Equipment Operations — Occupational Safety and Health Administration (OSHA)

    Paragraphs (a)(2), (b)(2), (c), and Table A.

    Federal crane power-line clearance assessment at 20 feet, de-energizing and grounding options, Table A voltage clearances up to 1,000 kV, non-conductive tag lines, and two-working-day utility voltage verification.

  4. Swimming Pool Equipotential Bonding Grid — Section 680.26(B)(2) — North Carolina Office of State Fire Marshal (Engineering Division)

    Section 680.26(B)(2).

    State electrical code interpretation detailing the 3-foot perimeter equipotential bonding grid, coverage of permanent inground and aboveground pools with or without paving, and the #8 bare copper conductor placed 18 to 24 inches from the pool edge.

  5. New York Sanitary Code Section 6-1.29 — Swimming Pool Design Standards — New York State Department of Health

    Structural stability, deck slope, and recirculation piping.

    State pool design code benchmarks covering full-and-empty structural loading, hydrostatic relief valves or underdrains, recirculation pipe velocity limits, continuous pipe support, and deck drainage slope and drain spacing.

  6. Residential Swimming Pool and Spa Permitting Checklist — City of Orlando

    Permits, Setbacks, Submittal Package, and Required Inspections.

    Municipal permitting example illustrating multi-permit submittals, 5-foot pool setbacks, offsite dirt haul-off, floodplain elevation rules, elevated deck accessory setbacks, 35 psi piping checks, and safety barrier thresholds.

  7. ASTM D448 — Standard Classification for Sizes of Aggregate for Road and Bridge Construction — ASTM International

    Section 1.1 Scope.

    Consensus aggregate classification defining standard size number designations and mechanical sieve ranges for coarse aggregate and screenings.

  8. ASTM D2321 — Standard Practice for Underground Installation of Thermoplastic Pipe — ASTM International

    Section 1.1 Scope.

    Consensus underground installation practice establishing stable granular embedment environments for buried thermoplastic piping.

  9. Fiberglass — Wikipedia

    Material reference covering fiber-reinforced plastic composition, E-glass fiber alkali limits, non-conductive thin-shell geometry, and polyester versus epoxy resin cure contraction.

  10. Swimming pool — Wikipedia

    Reference taxonomy identifying one-piece fiberglass shells alongside gunite shotcrete, concrete, and vinyl-lined vessels among the main in-ground swimming pool construction methods.